As COVID-19 restrictions hamstrung lumber producers and residential demand skyrocketed, lumber prices hit a record high in early May.
Now the lumber bubble is deflating. The market price for a thousand feet of board fell to $472 in the first week of August from the $1,600 high three months ago.
Lower prices have come as a relief for advocates of mass timber — a composite material made from wood but that is stronger than steel — who worried projects would be put on standby due to skyrocketing costs.
More on “Office”
Why the life sciences sector is heading for the cityOctober 03, 2022
How buildings have changed since 9/11September 10, 2021
7 technologies poised to change how buildings are madeAugust 24, 2021
“Short term, there are some mass timber projects that did not pencil because of the lumber costs,” says Carmen Van Liere, Vice President, Project and Development Services, JLL, who previously worked for Katerra, a firm that focused heavily on mass timber. “Others stayed on track because mass timber was a much larger part of an overall sustainability plan. Cost was a factor, but not the only one.”
Swinerton’s 25-story high-rise apartment project in Milwaukee remains on schedule for a July 2022 opening. When finished, the 284-foot Ascent will be the tallest hybrid mass timber structure in the world, slightly besting the 280-foot mixed-use building in Norway currently holding that record.
“We were fortunate to be released on procurement before the lumber hysteria set in, so we locked in the costs when we didn’t have that risk,” says Christopher Evans, President of Timberlab, the mass timber arm of Swinerton. “Overall, the momentum behind mass timber is awesome right now. The litmus test is that, it’s one thing to see a mass timber building in Seattle or Portland, progressive cities with a good lumber basket, but when we see projects show up in small town America, in the middle of Iowa and North Carolina, when public agencies and universities are looking at mass timber to lower carbon emissions and help the climate change crisis, it is an indication that mass timber is no longer just about early adopters.”
The supply chain disruptions over the past year affected all materials, including steel and concrete, and lumber has fallen the fastest, making it the most cost effective in many cases, Evans says.
“Lead-times for steel structural systems are a minimum of six to eight months right now; we can deliver mass timber projects in a quicker timeline,” he says.